Construction Act
Ontario.
Know your starting point.
The proper invoice sets the pace. The owner’s payment window and the notice window run alongside one another.
Prompt-payment framework in force
Scope comes before calculation.
Prompt-payment applicability depends on the contract and procurement transition rules, not just the date on an invoice. Check section 87.3. The rules changed again on 1 January 2026; use the applicable version.
The owner’s notice is Form 1.1. Different forms and timing apply further down the payment chain. See section 6.4 and O. Reg. 303/18.
Read the governing statute28days · ordinary owner payment14days · owner notice window
Eligible proper invoices only. Holdback, notices and counting rules can affect the result.
Try the deadline calculatorExplore the fundamentals.
General guides with Ontario contextKeep the primary sources close.
Construction Act, R.S.O. 1990, c. C.30 (consolidated)O. Reg. 303/18 (Forms 1.1-1.5, Form 6, Form 8)O. Reg. 264/25 (Adjudications under Part II.1)Prescribed construction-lien formsEdition: 4 October 2026. Regime status and linked instruments must be checked again before relying on a live deadline.