If you remember one thing

Record the triggering event. A date printed on an invoice is not proof of the date the owner received it.

In Saskatchewan

Builders' Lien Act (Prompt Payment Amendment)

The prompt-payment provisions began on 1 March 2022. Contract transition rules and exclusions matter; an old contract is not automatically brought into the regime by a new invoice.

The owner’s deadlines appear in section 5.4. Lower-tier notices have their own triggers and requirements; an owner’s notice does not serve as a contractor’s notice.

Read the governing source

The explanation below is a cross-province introduction. This jurisdiction note does not make every general example a rule for this province. Read the original payment deadlines guide for the shared explanation.

01

First, find the rule that applies

Start with the project, the contract and your place in the payment chain. Provincial and federal rules are different. Some projects are excluded, and transition rules can leave older contracts under an earlier framework.

This guide introduces the owner-to-contractor pattern used in Ontario, Alberta, Saskatchewan and Manitoba. It is not a universal Canadian payment schedule. B.C.’s enacted prompt-payment provisions are not yet treated as active here.

02

One invoice. Two windows.

For an eligible owner-to-contractor invoice in those four provinces, the ordinary payment window is 28 days and the owner’s notice-of-non-payment window is 14 days. Payment obligations remain subject to applicable holdbacks, a valid notice and other statutory qualifications.

These windows run from the legally relevant delivery event. Preserve the invoice, the transmission record and evidence of receipt or giving. A month-end accounting entry does not establish that event.

  • Payment window: when the payable amount is due.
  • Notice window: when the owner must give the required notice to dispute payment under that provision.
  • Counting rule: calendar days and the applicable last-day holiday rule, rather than a generic business-day calculator.
03

The next clock needs its own event

The ordinary seven-day payment cascade is generally triggered by actual receipt of payment for the relevant subcontract work. It does not automatically begin on the owner’s forecast payment date.

When full payment does not arrive, other payment and notice duties may still arise. A contractor cannot safely assume that an unpaid owner invoice pauses every obligation to subcontractors.

04

What to do with a date

Use a calculated date as a prompt to check your evidence and the governing rule. Keep a separate record of payments, notices, service and changes. If a deadline may be missed or disputed, obtain advice while there is still time to act.

The free calculator shows two ordinary owner-level windows from your confirmed facts. It does not serve notices, monitor a project or determine whether an invoice is legally proper.

Put it into practice

Payment deadline calculator

Apply the explanation to a focused situation. Free, with sources and assumptions visible.

Try the free tool

Sources & scope

These are general educational explanations, not advice on a specific contract. Check the version of the law that applies to your project. This edition has not been represented as independently reviewed by a lawyer.

SaskatchewanBuilders’ Lien Act, Part I.1Source register & editorial method